Three paths

How your kit gets installed

Choose the path that matches your comfort with electrical work and what your local authority will allow. Every path starts with the same design review.

Self-install

You mount the array and pull the DC wiring with our written guide, and a licensed electrician makes the final AC connection and signs the permit. CheapCST, and allowed in many jurisdictions for the homeowner.

Confirm with your local building department first. Some cities require a licensed installer for the whole job.

Your own electrician

You hire a local licensed electrician or solar contractor. We send the single-line diagram, equipment datasheets, racking engineering and the bill of materials they need to bid and to pass inspection.

Most buyers use this path. Expect the installer to quote labour, permit handling and any panel upgrade separately.

Our partner network

Where we have a vetted partner in your area, they handle the roof work, electrical connection and inspection. Availability depends on your region and their schedule.

Not available everywhere. Ask us before you order so the quote you receive matches reality.

Installation paths: we supply complete kits and can refer you to a licensed local electrician. Most kits are installed in 1–3 days; permitting and interconnection take additional time depending on your jurisdiction.

Sequence

The four stages after you order

Durations are typical, not promises: the local authority and your utility set two of the four clocks, not us.

1

Design review

We check the kit against your bills, roof photos and electrical panel. If a different size fits better, you hear it before the crate is built.

2

Permit & interconnection

Your installer or electrician files the building permit and the utility interconnection application. You will be asked for a site plan and equipment datasheets, which we supply.

3

Delivery & install

The kit arrives curbside in crates. Racking goes up first, then panels, then the inverter and the AC connection. Most homes take one to three days on the roof.

4

Inspection & PTO

The local authority inspects, then the utility issues permission to operate. Only then should the system be switched on and the meter recorded.

Timeline

How long each stage actually takes

Design review
2–3 business days after we receive bills and photos
Equipment lead time
2–5 business days to crate, 3–7 in freight transit
Building permit
1–6 weeks, set by your local authority
Installation
1–3 days for a residential roof mount
Inspection
1–3 weeks for a slot, varies by city
Permission to operate
1–4 weeks after inspection, set by your utility

These timelines are based on typical US residential projects across 42 states. Your actual timeline depends on local permitting, utility interconnection and inspector availability.

What we send

Documents in the crate

  • Bill of materials with every component and quantity
  • Single-line electrical diagram for the permit package
  • Panel and inverter datasheets, UL certificates and rapid-shutdown documentation
  • Racking layout, clamp spacing and engineering letter where required
  • Step-by-step installation guide with torque values
  • Monitoring setup instructions and our support number
What stays local

Your side of the paperwork

  • Building or electrical permit from your city or county
  • Utility interconnection application and net-metering enrolment
  • Signed contract with the licensed electrician doing the AC work
  • Structural review if the roof is old, steep or carrying snow load
  • HOA or historic-district approval where it applies
  • Homeowner insurance notification, if your policy requires it
Code

The rules an inspector will check

These are the items that most often hold a system up. Your electrician owns them, but you should recognise the terms.

Rapid shutdown

NEC 690.12 requires the array to drop to a safe voltage near the modules for firefighters. Most modern inverters and module-level electronics include this; the label must be at the service panel.

Disconnects and labelling

A visible, lockable AC disconnect is commonly required, plus placards identifying the PV source, the maximum voltage and the shutdown device.

Structural loading

Roof attachments must handle wind uplift and snow load for your region. Engineered racking with a stamped letter is the cheapCST way to avoid a failed review.

Interconnection limits

Utilities cap how much generation can sit behind a service. A 20kW system on a small residential service may need a dedicated meter or a study before approval.

Tell us your address and we will tell you what is possible

Send your ZIP code, a photo of your electrical panel and three months of bills. You will get the kit that fits, the documents your electrician needs, and an honest answer about the permit timeline.